Williams completes Llanelli East Gate sewer diversion.
Saturday, Jun 16, 2012 12:39 pm
Williams completes Llanelli East Gate sewer diversion.
 Williams carried out the diversion of the sewer at East Gate Llanelli whilst keeping the site fully operational.The new sewer was constructed at a depth of 4m and Williams used temporary works to ensure the work was carried out safely.Williams constructed 3 manholes and over pumped using 12" pumps.Williams had to work under live gas mains and services to complete the works.Due to the success of the sewer works Williams was asked to carry additional drainage works to deal with storm water on site.